Haslet - Alliancetexas/Haslet/Haslet Accessibility Improvement Project (ATHAIP)

Project Cost:  $64,476,000

Requested Funding: $2,568,000 (2006 TPB Discretionary Funds from Precinct 3)

Estimated Completion Date: December 2024 (Haslet Parkway-Intermodal Parkway Connection to be open by March 31, 2023)

The project is comprised of three components: (1) construction of Haslet Parkway as a new 4-lane divided thoroughfare from I-35W to FM 156 at Avondale-Haslet Road; (2) extension of Intermodal Parkway as a 4-lane divided thoroughfare from its current terminus south to the new Haslet Parkway facility; and (3) widening of Avondale-Haslet Road to a 4-lane divided thoroughfare from FM 156 to the Haslet city limits.

Contact:  Billy Havard, 817-399-4303

Map of ATHAIP

Project Website